Table 4. Milestone planning matrix for the RestoLight project

PB IdWIProject kickoffDesign concept approvedPlatform selectedDesign completedPlatform availableRelease 1Beta testing launchedRelease 2Beta testing results reviewedRelease 3ATP approvedATP completedSystem deployedCustomer sign-offProject closedWI effort
1.aUX design13010 140
1.b.1Select Platform110 110
1.b.2Install development stack     20         20
1.b.3Set-up build distribution     30         30
1.cBrowse menu 200200
1.c.2.1Add item to order 9090
1.c.2.2Remove item from order 5050
1.c.2.4Order 5050
1.c.2.5Clear order 1010
1.c.3.1Add tip     40         40
1.c.3.2Pay with credit card 8080
1.c.3.3Pay with cash 5050
1.c.4.4Update all devices 5050
1.c.3.3Customize       100       100
1.c.4.1Add item to menu       60       60
1.c.4.2Remove item from menu       40       40
1.dBeta testing 401050
1.c.3.4Pay with loyalty points         30     30
1.c.4.3Modify menu item         60     60
1.c.5Refactoring & Feedback 100200300
1.eAcceptance testing 5050100
1.fSystem Deployment 150150
 Work package effort013011010067040300102905050150001810